For landowners on FERC-regulated pipeline projects

Pipeline inspection and restoration support for landowners.

Central Land Consulting inspects and documents pipeline right-of-way conditions and reports findings to FERC, so impacted properties are restored to pre-construction condition.

CLC drone documentation
~700Landowner matters at FERC
2015Fighting for landowners since
6States: OK, IL, MO, WV, PA, OH
5FERC-regulated pipeline projects

Why it matters

Independent documentation for landowners.

Restoration status on pipeline projects is largely reported by the operator. Landowners benefit from an independent record of what is actually happening on their property.

We document compaction, topsoil loss, drainage problems, buried rock and debris, and revegetation, and provide FERC with clear, verifiable findings.

What we do

Our services

From pre-construction through final restoration.

Construction Monitoring

On-the-ground inspection during construction so violations are caught and documented while they happen, not after.

Advanced Compliance Inspections

Tract-by-tract evaluation against the FERC Plan and Procedures, certificate conditions and state agricultural agreements.

Restoration Determinations

Compaction, topsoil loss, drainage, rock and debris, revegetation, documented with remediation plans to pre-construction condition.

FERC Filings & Advocacy

We submit findings to FERC and work alongside landowners' counsel.

How it works

How it works

  1. 1

    Contact us

    Tell us what's wrong with your land and which project crossed it.

  2. 2

    We inspect

    Field inspection, photos, soil and drainage findings, mapped to the right-of-way.

  3. 3

    We file

    Findings go on the FERC record with specific deficiencies and a remediation plan.

  4. 4

    We follow up

    Follow-up inspections until restoration is complete.

From the field

Field documentation

Photos taken by CLC during inspections and test pits on landowner property.

Oklahoma

Midship Pipeline

A summary of restoration filings and FERC actions on the Midship Pipeline project.

View case summary
  1. FERC orders work stopped on the North Spread for failing environmental conditions.
  2. Midship claims 94% restoration; project placed into service.
  3. Order on Environmental Compliance: fix outstanding tracts within 60 days.
  4. Congressional hearing: “Pipelines Over People (Part II).”
  5. FERC issues Order to Show Cause over buried rock and debris.

Projects

Projects

Oklahoma · Active

Midship Pipeline

Cheniere Energy. Compliance order, show-cause order, House oversight hearing.

View case summary
Illinois / Missouri · Active

Spire STL Pipeline

65 miles. Illinois Department of Agriculture documented AIMA violations; certificate vacated by the D.C. Circuit in 2021.

West Virginia / Pennsylvania

Dominion Supply Header

About 37.5 miles of pipeline plus compression modifications.

West Virginia

Mountaineer XPress

About 165 miles, Marshall County to Wayne County, with three new compressor stations.

Ohio / Michigan

NEXUS Gas Transmission

255-mile interstate line from Ohio toward the Dawn Hub in Ontario.

Pipeline on your property?

Contact us to discuss an inspection.

Contact us

Request an inspection

Tell us about your property and the pipeline project involved.

info@centrallandconsulting.com Canton, Ohio. Serving landowners nationwide.